Microsoft Project 2003 documentation states that a task with Priority =
'1000' will not be resource leveled. So I assigned a Priority = '1000' on
some tasks I do not want delayed by resource leveling. When I resource
leveled, it delayed these tasks even though their priority = '1000', whether
I used 'Priority, Standard' or just 'Standard' for Leveling Order. How do I
prevent resource leveling from delaying these tasks?