K
Kay
Hi
I wanted to enter two resources, A and B, to spend A=20% and B=30% per
day
on support issues.
So only 70% and 80% are free for real work
I entered a task
Other work
in MSP and then said:
Fixed work
and entered A and B with the percentages as resources.
But MSP does not do as I expected.
if I go in the resource usage, i see weird things.
A has 0.3d per day mentioned, but not every week.
Some weeks, Monday is empty.
B has one mention on Monday and then some weeks nothing.
What am I doing wrong?
How can I enter it?
Thanks
Kay
I wanted to enter two resources, A and B, to spend A=20% and B=30% per
day
on support issues.
So only 70% and 80% are free for real work
I entered a task
Other work
in MSP and then said:
Fixed work
and entered A and B with the percentages as resources.
But MSP does not do as I expected.
if I go in the resource usage, i see weird things.
A has 0.3d per day mentioned, but not every week.
Some weeks, Monday is empty.
B has one mention on Monday and then some weeks nothing.
What am I doing wrong?
How can I enter it?
Thanks
Kay