Un Submitted Timesheets

C

Chris

Hi

We have just gone Live using Project Server with Timesheets (using Managed
Periods) however when any of the Users Log in they see several messages
informing they have not submitted a timesheet for previous periods. (The
periods are before we went live).

Any advice on how this can be cleared would be appreciated.

Regards
 
D

Dale Howard [MVP]

Chris --

You need to update both Project Server and Microsoft Project Professional to
SP2a. Hope this helps.
 
C

Chris

Will do - thanks Dale.

Regards
--
Chris


Dale Howard said:
Chris --

You need to update both Project Server and Microsoft Project Professional to
SP2a. Hope this helps.
 
C

Chris

I have users that have submitted timesheets and their updates have been
udpated in the project plan, but their timesheet status still shows
unsubmitted. We are using PS 2003 SP2a. Any ideas?

thanks.
 
Top