Unabale enter Acual hours

K

Kamran Abadehee

Hi there,

I just moved tasks from several projects to new created projects (to split
by clients). when I did that "default method for reporting progress " was on
"Actual work done and work remaining: Resources report the actual work done
and the work remaining to be done on each task." after movment I realyzed
staff can't enter acuals in PWA.
I changed methode to "Hours of work done per day or per week: Resources
report the hours worked on each task during each time period." right now any
new tasks are working well but I still have problem on old ones.

Is there any idea?

Thanks

Kamran
 
Top