Unable to Edit, Copy, or Delete Custom Group

B

BillV

I need some serious help and I am willing to send my project plan so whomever
wishes to help can get a detailed look at my problem. Here it is: I have
taken the place of an individual who left no information on how to at all.
There is one particular hurdle I am unable to overcome. When I add a task in
Gantt View under an exisiting Summary task or otherwise, everything appears
normal. However, when I view the additions through the Custom View (SEP 6
Col Progress) , the added tasks appear at the top of the Custom View not
associated with an Task. I have tried to find out what makes this Custom
View so custom but, I cannot copy, edit, or delete it, not in any part of
Project. The Custom View has become the defacto view for the department. If
anyone thinks they can crack this mystery please let me know, I be grateful.
 
J

Jan De Messemaeker

Hi,

I think I know HOW to edit it, but why you can't edit it I am clueless.
You can send the file to jandemesATprom-ade.be, I'll have a look
(Replace the AT by @ of course)
Greetings,

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 