I am using MS Project 2003 in an enterprise environment. I have
created and published a project to the project server.
When viewing the timesheet for a single project through Project Web,
some tasks permit entry of daily "actual work" and "remaining work".
Other tasks however permit entry of "remaining work" only.
Can someone please help identify why this timesheet/task inconsistency
exists?
Note: Not sure of the relevance, however I have baselined the plan and
applied a status date in the Project Information.
Thanks in advance.
created and published a project to the project server.
When viewing the timesheet for a single project through Project Web,
some tasks permit entry of daily "actual work" and "remaining work".
Other tasks however permit entry of "remaining work" only.
Can someone please help identify why this timesheet/task inconsistency
exists?
Note: Not sure of the relevance, however I have baselined the plan and
applied a status date in the Project Information.
Thanks in advance.