I am faced with a similar issue here - I have two project
plans both involving resource X (assumes tasks are
levelled). When resouce X logs into Project Web Access
2002, he is able to view tasks from Project 1 but not from
Project 2. Anything that I am missing here ?
 
D

Dale Howard [MVP]

Sri --

Has the project manager of Project 2 actually published the resource
assignments (Collaborate - Publish - New and Changed Assignments)? If not,
those assignments will not be seen by resource X on the View My Tasks page
(the timesheet). Hope this helps.
 
S

Sri

Thanks for your help Dave. Actually it was a conflict of
resources between the PWA resource table and the MPP file.

Thanks again..
 