Unassigned!!!

J

John

Could someone tell me why all of a sudden my project plan
has unassigned as the resources on my tasks? I too have
lost my whole team like the previous post. HELP!!!!

J
 
G

Gérard Ducouret

Hello John,
Didn't you erase the "Resources Names" column (close to the Gant Chart)
Didn't you erase all the rows in the Resource Sheet : View / Ressource sheet
?
Take care of the DEL key : it's often dangerous !

Gérard Ducouret
 