We have developed a 6.5 hour per day calendar on which to plan - with the
holidays that affect it.
When we publish this plan to the 2003 server, some resouces - but not all -
have their calendars changed to another calendar. This calendar is an 8 hour
day one, and the holiday input is not far enough out to give us the warm and
fuzzies, and we have no idea who/how can keep the holidays far enought out to
avoid working have deliverables due on Christmans, so to speak.
People with server access - like me - can not correct the server calendar
"modification", and the plan owner can not change it either.
holidays that affect it.
When we publish this plan to the 2003 server, some resouces - but not all -
have their calendars changed to another calendar. This calendar is an 8 hour
day one, and the holiday input is not far enough out to give us the warm and
fuzzies, and we have no idea who/how can keep the holidays far enought out to
avoid working have deliverables due on Christmans, so to speak.
People with server access - like me - can not correct the server calendar
"modification", and the plan owner can not change it either.