Hi,

There are some Tasks lines 'hidden' - would you know how to unhide them?

Thanks and best regards,

Joanna
 
R

Rob Schneider

Joanna,

As far as I know, there is now to "hide" tasks (as in how Excel will
hide a row); but Project does have two features which may be at work here:

1. Tasks can be shown in a hierarchy and you can open and close
subtasks. Look for a "+" to the left of the summary task name to open.

2. There could be a filter applied. See Menu: FilteredFor/... Remove
the filter to take it off (it is there).


--rms

www.rmschneider.com
 
R

Rob Schneider

Joanna,

As far as I know, there is no way to "hide" tasks (as in how Excel can
hide a row); but, Project does have two features which may be at work here:

1. Tasks can be shown in a hierarchy and you can open and close
subtasks. Look for a "+" to the left of the summary task name to open.

2. There could be a filter applied. See Menu: FilteredFor/... Remove
the filter to take it off (it is there).



--rms

www.rmschneider.com
 
L

Larry Christofaro

If you are referring to Project Server 2003 and the task sheet, you have a
couple options:
* Have the project manager republish the task (not just publish, but
republish)
* If the task changes after the user hides a task (work or date changes),
that task will reappear.
 