A
andrewbettany
Hi,
We had a "project meeting" today - we have single big project coming up and
we are still evaluating whether MSP is going to give us the majority of the
answers....
We are not savvy with VBA, so we cannot do anything too tricky.
I really appreciate your advices to my couple of questions.
The 2nd question is how do you recommend we obtain a unique numbering system
for our tasks?
We would like be able to refer our remote users to a specific task, using a
reference number, based on a copy of a project that may be a out of sync,
i.e. a month or so out of date (but 95% complete).
On first appearance WBS looks ideal.... but these numbers change as we add
new tasks, also the task ID changes likewise and using a number code as part
of the task name is a non starter.
Is there another recommendation (like is each task given a unique ID), or is
WBS really the only way to achieve this - if so how could we avoid it
changing when we add a new task item?
Kind regards
Andrew in Sheffield (UK)
We had a "project meeting" today - we have single big project coming up and
we are still evaluating whether MSP is going to give us the majority of the
answers....
We are not savvy with VBA, so we cannot do anything too tricky.
I really appreciate your advices to my couple of questions.
The 2nd question is how do you recommend we obtain a unique numbering system
for our tasks?
We would like be able to refer our remote users to a specific task, using a
reference number, based on a copy of a project that may be a out of sync,
i.e. a month or so out of date (but 95% complete).
On first appearance WBS looks ideal.... but these numbers change as we add
new tasks, also the task ID changes likewise and using a number code as part
of the task name is a non starter.
Is there another recommendation (like is each task given a unique ID), or is
WBS really the only way to achieve this - if so how could we avoid it
changing when we add a new task item?
Kind regards
Andrew in Sheffield (UK)