Mandar Mehta
I need to plan the work assignment on a monthly basis
using a contour template. e.g. I want to plan earthwork
excavation units of say total 1,00,000 cum to be executed
in June (say 10,000 cum), July (15,000 cum), Aug (20,000
cum), Sept (20,000 cum), Oct(20,000 cum) & Nov (15,000
cum). How can I achieve this in MSP2k? I dont want the
conversion of these units to time equivalent.