greg
OK,
this should be an easy one.
If I create a task. Work = 10 hours
then I assign person 1 and person2 to the task.
In the resource usage view I assign p1 = 2 hrs and p2 = 8 hrs
back in the task the units for both are 100%
So is units like making a priority?
Because the units are not 20% and 80%. For a distribution.