units

G

greg

OK,
this should be an easy one.

If I create a task. Work = 10 hours
then I assign person 1 and person2 to the task.
In the resource usage view I assign p1 = 2 hrs and p2 = 8 hrs

back in the task the units for both are 100%

So is units like making a priority?
Because the units are not 20% and 80%. For a distribution.
 
J

Jan De Messemaeker

Hi,

It IS an easy one.
The task type must be fixed units (the default)
Double Click on the task, in Task Information click advanced, set task tyep
to fixed duration if that's what you want.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 
G

greg

thanks,
I will look

Jan De Messemaeker said:
Hi,

It IS an easy one.
The task type must be fixed units (the default)
Double Click on the task, in Task Information click advanced, set task
tyep to fixed duration if that's what you want.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 