I am working with Project Server 2007 and have run across a problem where
when one creates a Risk or Issue (web browser based) and choses to link it to
a Task that is numbered 101 or greater an Unknown Error dialogue is returned
and the link does not happen.
I have come up with a work-around where one can select as many tasks
numbered 101 or greater as they chose (I added upto 5) and then move to the
previous task page (tasks numbered 1 to 100) and then commit the link. This
seems to work fine.
Has anyone got any thoughts on this?
Regards,
George
when one creates a Risk or Issue (web browser based) and choses to link it to
a Task that is numbered 101 or greater an Unknown Error dialogue is returned
and the link does not happen.
I have come up with a work-around where one can select as many tasks
numbered 101 or greater as they chose (I added upto 5) and then move to the
previous task page (tasks numbered 1 to 100) and then commit the link. This
seems to work fine.
Has anyone got any thoughts on this?
Regards,
George