Put more simply,
some projects i am dealing with need (i think) to have the scheduling option
"Tasks will always honor their constraint dates" enabled because when this is
disabled, and the project is linked to a common resource pool that many other
projects share, it results in unrealistic finish dates that are nowhere near
their original dates, due to the fact that some predecessor tasks will
inevitably be entered as finished (entered as 100% complete) at a date that
is earlier than their original estimated finish date. From our discussion to
date, I am assuming that the unwanted duration changes that i am reporting to
you are a result of;
- the constraints (FNET, etc...) placed on some of the tasks
- scheduling options such as "Tasks will always honor their constraint
dates" enabled.
My question is;
Is it possible to set a project file that behaves in the following way;
- fixed durations never change, unless changed manually.
- Tasks always honor their constraint dates.
If so, which settings do i require?
If not, how can i configure a project file to behave as close as possible to
the above mentioned one?
Many thanks for all your assistance thus far,
Regards,
EM