update a Custom enterprise field

M

mmatthius

The problem I am having is I created a new custom enterprise date field
called updated date and I get it to appear in the view for the
timesheet but it is not updateable. What we want is allow the fielding
managers to input a purposed new date for the start of the task. But
right now it is grayed out. It is possible to allow a resource to
update this new task through PWA.

Thanks for your help,
Matt
 