Hi everyone,
I create a task custom field named taskvalue, that the team members must
update and report.
In order to the able the resource to update the field taskvalue, i added the
field to the view in my tasks, the field is updated by the resource and
submited to the project manager.
The project manager can view the task update, if he see the details of the
update appears taskvalue ---> 30, and the update can be approved.
But when he tires to publish the update by project pro or the pwa, the
change is not updated in the task, appears the old value.

It is OK? what i try is wrong? is there a way to do this?

Thanks,
Jose X Perez
 