J
Jose M. Dominguez
Hello:
I've been using EPM 2003 with managed time periods.
Now I want to include some old projects (MS Project 2000)
with actuals in them in my server. I've activated non
managed periods mode so that I can feed actuals from
project professional 2003, but each time I publish a
project those actuals are not included on timesheets.
I have checked the adjust actuals permission for me as
project manager and administrator.
What else I'm missing?
Thanks
Jose
I've been using EPM 2003 with managed time periods.
Now I want to include some old projects (MS Project 2000)
with actuals in them in my server. I've activated non
managed periods mode so that I can feed actuals from
project professional 2003, but each time I publish a
project those actuals are not included on timesheets.
I have checked the adjust actuals permission for me as
project manager and administrator.
What else I'm missing?
Thanks
Jose