Update all

J

Jag

The MS Project Server 2003 implemention uses managed time periods to report
time on a weekly basis. When a resource enters time across multiple weeks
(Week1 and Week2 for example) and uses the update all button for week2, MS
Project Server submits only the hours entered for week2 to the resource
manager for Approval while the hours for week1 and week2 are submitted to the
project manager. Is there a work around for this?
 
M

Marc Soester [MVP]

Hi Jag,

I assume that your managed time period is set to weekly. That means that
your resources should report their time each week. Thats why you have this
issue. I dont think there is a workarround. Maybe it is possible that your
resources report on a weekly basis. Alternetafly you could set your managed
time period to report every 2 weeks.
Hope this helps
 
Top