Hi
Recently some resource where transfer from one project to my project. I
have assigned a bunch of task to this guy. Now, when he goes in the PWA to
update his tasks, the notification is not sent to me but to another manager.
I have tried to do a1 "Republish Assignment" and check the "become the
manager of these tasks" check box but it does not change anything. What do I
have to do so that all the notifications and approval request are sent to me?
if it can help, when I go in the resource sheet, There is a "!" next to the
name of this resource and a note saying that "This resource should be leveled
on a Day by Day setting". What does it mean and what can I do to fix this?
it seems that somewhere this resource is assigned to another project and is
not part of my team... How to fix this?
thanks a lot
Recently some resource where transfer from one project to my project. I
have assigned a bunch of task to this guy. Now, when he goes in the PWA to
update his tasks, the notification is not sent to me but to another manager.
I have tried to do a1 "Republish Assignment" and check the "become the
manager of these tasks" check box but it does not change anything. What do I
have to do so that all the notifications and approval request are sent to me?
if it can help, when I go in the resource sheet, There is a "!" next to the
name of this resource and a note saying that "This resource should be leveled
on a Day by Day setting". What does it mean and what can I do to fix this?
it seems that somewhere this resource is assigned to another project and is
not part of my team... How to fix this?