Update Fields

T

TR

I want to update Text1 with data from Percent Complete
everytime it changes, what would be the easiest way to
accomplish this without slowing performance.
Thanks in advance
TR
 
J

Jan De Messemaeker

Hi TR
If you are in P2000+, put a formula in the text1 field.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
Project Management Consultancy
Prom+ade BVBA
32-495-300 620
 
T

TRS

Jan,
I want to take %work complete and move it into Physical %
Complete, this would happen only when % work complete
changed.
Thanks
T.R.
 