Is it possible for a team member to update (% complete) a milestone (task
with zero duration) in PWA?

thanks,
 
D

Dale Howard [MVP]

MP --

Yes and no. You CAN assign milestone tasks to resources and the tasks will
appear on each resource's My Tasks page. The resource CANNOT update the %
Complete, however. Instead, the resource can simply select "Done" or "Not
Done" from a pick list in the Progress column ("Not Done" is the default
status of a milestone until the resource marks it as "Done"). Hope this
helps.
 
M

MP

Yes, it did help.
Thanks

Dale Howard said:
MP --

Yes and no. You CAN assign milestone tasks to resources and the tasks will
appear on each resource's My Tasks page. The resource CANNOT update the %
Complete, however. Instead, the resource can simply select "Done" or "Not
Done" from a pick list in the Progress column ("Not Done" is the default
status of a milestone until the resource marks it as "Done"). Hope this
helps.
 
B

Berni

Hi, I'm new with PWA…

This discussion is helpful, but in what view can I find this field
"Progress" column ?

Thanks

Ben
 
D

Dale Howard [MVP]

Berni --

You can't see this column in Project Server 2003. It's only available in
Project Server 2007. Hope this helps.
 