Update My Tasks with different field PS2003

P

Patrick

Hi, I'm trying to make the "Revised Start Date" and Revised Finish Date
fields modifiable. They are already in the MY TASKS view. They are grayed
out however. I have followed the directions to add them to the view and
allow them to be edited (in Proj. Pro, Tools, Customize, Published Fields,
allow them to edit, etc,). Then I republish all information and go back to
PWA and they are still grayed out.

Any idea? Thanks!
 
D

Dale Howard [MVP]

Patrick --

When you republished, did you click Collaborate - Publish - Republish
Assignments? If not, this is the type of publishing operation you must do
to activate these fields for any existing project. Let us know.
 
J

Jonathan Sofer

Did you set the field to be published as a Task level or Assignment level
field?

Jonathan
 