N
Nathalie
I would like your advice on the update of actual hours and some help on
several issues I had.
I have a task with fixed duration and five people assigned.
I want to update thair actual hours. To do that, I update the project with
the status date as of today. The Actual work is automatically set as what was
planned.
Then, I update manually the actual hours for each resource in the task usage
view.
Sometimes, it happens that the end date is modified or the status date of %
complete is changed. For example today is 13th and my black line of progress
is modified and goes until the 6th.
I would like to know what I am doing wrong.
thanks
Nathalie
several issues I had.
I have a task with fixed duration and five people assigned.
I want to update thair actual hours. To do that, I update the project with
the status date as of today. The Actual work is automatically set as what was
planned.
Then, I update manually the actual hours for each resource in the task usage
view.
Sometimes, it happens that the end date is modified or the status date of %
complete is changed. For example today is 13th and my black line of progress
is modified and goes until the 6th.
I would like to know what I am doing wrong.
thanks
Nathalie