J
Johan Caljé
Is there a way to have one project, where some users update their tasks with
% complete and other users with work.
We want to use it for tasks that are done by an external company (with fixed
price), but we want them to update on task % completation, to track progress.
Other resoures that are on the project should enter work hours.
PWA seems to give only one reporting method per project...
% complete and other users with work.
We want to use it for tasks that are done by an external company (with fixed
price), but we want them to update on task % completation, to track progress.
Other resoures that are on the project should enter work hours.
PWA seems to give only one reporting method per project...