In the Web Access Timesheet View (Accessed via the Tasks top navigation
bar), team member by default can only update the % Work Complete and
Remaining Work column.
It is quite often that people ask whether they can update other field.
One of the common requests is for team member to update Actual Start date.
Here is how you do it...
<a href="http://workspaces.gotdotnet.com/jyps"
target="_blank">http://workspaces.gotdotnet.com/jyps</a>