JulieS said:
Hi Anita,
Those settings control how Project updates % Complete on tasks that should
have been in progess (but not finished) as of the status date (date appearing
in the Update Project dialog box). The choice set 0-100% complete would mark
a task that should have been started by not completed as of the date the
appropriate % complete. For example, a 10 day task that that started on 28
April 2005 should have been 50% complete as of 4 March 2005. If I choose
"set 0-100% complete it is marked as 50% complete.
If I choose 0 or 100% complete only the same task with the same update date
(4 March) the % complete is not touched by Project because it is not
scheduled to be completed until 11 March 2005.
Hope this helps. Let us know how you get along.
Julie
Julie,
When I first read your explanation, (I didn't see it in my newsreader
until after I posted mine), I thought I had missed something. However on
re-reading it I noted two things. First your example has a really
strange task that hasn't started yet (i.e. 28 April 2005) but should
have been 50% complete as of 4 March 2005. How you do dat? The second
thing I realized is that our responses say the same thing. You just
provide more of an explanation and that is better.
John