P
Predrag
Hi,
I have these problems when updating project progress.
If a resource has sent hours for approval for 3 weeks, but
I want to update my project with hours for only the first
2 weeks but not for the third one, is there are any way to
do it. The reason for this is when we do our month end
(for example for January), we would do it first few days
of February. By that time a resource could already have
hours entered in timesheets for February, for the same
assignment, but I don't want to have them imported into
Project.
The second problem is once I update project with the hours
that resources have entered into timesheets, and let say
by mistake I delete some of those hours is there are a way
for me to get those hours again. It seems that I will be
able to do this only if a resource modified hours in the
timesheets and then sends an update to me.
Thanks,
Predrag
I have these problems when updating project progress.
If a resource has sent hours for approval for 3 weeks, but
I want to update my project with hours for only the first
2 weeks but not for the third one, is there are any way to
do it. The reason for this is when we do our month end
(for example for January), we would do it first few days
of February. By that time a resource could already have
hours entered in timesheets for February, for the same
assignment, but I don't want to have them imported into
Project.
The second problem is once I update project with the hours
that resources have entered into timesheets, and let say
by mistake I delete some of those hours is there are a way
for me to get those hours again. It seems that I will be
able to do this only if a resource modified hours in the
timesheets and then sends an update to me.
Thanks,
Predrag