G
George
I have found that it is possible to update %Complete
values in summary tasks. I did not think this was
possible, as summary task values are calculated values
from the underlying tasks. When this happens, how does
Project recalculate the %Complete values of the underlying
tasks? Or, is this a malfunction?
Thanks.
values in summary tasks. I did not think this was
possible, as summary task values are calculated values
from the underlying tasks. When this happens, how does
Project recalculate the %Complete values of the underlying
tasks? Or, is this a malfunction?
Thanks.