Updates Not Approved Get Overwitten

C

Chris Walsh

If a resources has updates waiting for approval by the Project Manager, a Project Manager makes changes to the task and republishes all assignments, the data waiting for approval and update gets overwritten with previous values.

1: Two things, if it overwrites the data, there should be no reason to update the tasks cause you have overwritten the changes.

2: I don't think the data should be overwritten by the simple fact of re entering the data if a heap of updates get sent through and the Project Manager decides to change a published field, all the data the resources have change is now useless!!

Which should it be??
 
G

Gary L. Chefetz \(MVP\)

Chris:

You have to accept updates first, before making changes that require
republishing.

--

Gary L. Chefetz, MVP
"We wrote the book on Project Server
http://www.msprojectexperts.com

-
Chris Walsh said:
If a resources has updates waiting for approval by the Project Manager, a
Project Manager makes changes to the task and republishes all assignments,
the data waiting for approval and update gets overwritten with previous
values.
1: Two things, if it overwrites the data, there should be no reason to
update the tasks cause you have overwritten the changes.
2: I don't think the data should be overwritten by the simple fact of re
entering the data if a heap of updates get sent through and the Project
Manager decides to change a published field, all the data the resources have
change is now useless!!
 