project plan doesn't get updated after I approve a task update from a resource.
David Piatt said:Good Morning Gary,
I used the project guide to build a couple and built a couple without.
Yesterday, none of them worked. Today, I am having luck with all but the
first one that I created.
The error in "My Queued Jobs" from yesterday and the days before states:
Reporting message processor failed The INSERT statement conflicted with
the
FOREIGN KEY constraint "FK_MSP_EpmAssignment_ProjectUID_TaskUID". The
conflict occurred in database
I have no idea why some of the projects are working today. I didn't
change
anything and the sys admin says he didn't do anything either. Can you
explain the error statement so I can feel comfortable that I don't have an
intermittent problem?
Thanks