When I try to update with actuals (against the baseline) in MS Project 2003,
the actual start and finish dates are displayed as pound/sharp (##)
characters rather than the dates I've entered. On mouse-over, the dates are
visible, but not when I move the cursor away.

Why?
 
J

JulieS

Hello Janick,

The column is not wide enough to show all values. Double click in
the column heading to "best fit" the column width to the widest
entry.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 
J

JulieS

True enough Trevor -- but how easy or hard it is for someone to
answer a question doesn't really matter. They are all still
questions from people who need assistance -- and that's why we're
all here :)

Julie

"Trevor Rabey - Perfect Project Planning"
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top