Upgrading Project 2000 to 2003

M

Mark E. Read

What is the best reference that details how calculations
are done differently between Project 2000 and Project
2003? I am interested in duration, cost and work
calculations that may change as projects are converted
from 2000 to 2003.

Thanks for your help!

--Mark
 
R

Rod Gill

That I know of there are no differences in those calculations.

In Project 2000 resave the baseline. Make sure the calendars in Project 2003
are the same, then import. Check the Tracking Gantt Chart to see if any
dates have changed (no longer = baseline dates).
 