Uploading - Change in Duration2

D

DV

Hello ALL,
I tried uploading a Project Plan in Project Server 2002.
I have a calendar that is 24 hours/day.
There is a problem that I am facing uploading the plan.
When I upload the plan, Actual hours worked remain the
same but the Duration ( in days ) changes.There is a
variance between the Baseline Duration and Actual
duration once the plan is uploaded, What could be the
problem?
I am still facing the same problem.
The hours remain the same but working days changes.
My project plan has 24 hour calendar.
Any help appreciated.
Thanking you in advance
DV.
 
Top