M
Mat
Hi All
we are using locked down actuals and posting timesheets to plans once a week
and as part of the posting process i have been rolling forward estimates not
used into the next weeks time period by manually putting zero's in the actual
work field in the resource usage view.
For some reason even after saving and republishing - all this effort seems
to be for nothing as the estimates seem to reset to where they were...
Can anyone tell me why this isnt working - im not a happy bunny.....
cheers
Mat
we are using locked down actuals and posting timesheets to plans once a week
and as part of the posting process i have been rolling forward estimates not
used into the next weeks time period by manually putting zero's in the actual
work field in the resource usage view.
For some reason even after saving and republishing - all this effort seems
to be for nothing as the estimates seem to reset to where they were...
Can anyone tell me why this isnt working - im not a happy bunny.....
cheers
Mat