A
Andrew
Hi,
I am getting the circular reference error message on the last task on a
project plan. I have tried the following:
1, Removed all predecessor and successors for the task. Error message still
appears.
2, Deleted the the task, circular reference moves up to the previous task
3, Deleted the roll up that the task was a child of, circular refence moves
up to the last task of the previous roll up.
4, Deleted that roll up. Circular reference is now on a task that does not
exist in the plan!?!?!
Any handy hints, tips or plain old fixes would be appreciated
I am getting the circular reference error message on the last task on a
project plan. I have tried the following:
1, Removed all predecessor and successors for the task. Error message still
appears.
2, Deleted the the task, circular reference moves up to the previous task
3, Deleted the roll up that the task was a child of, circular refence moves
up to the last task of the previous roll up.
4, Deleted that roll up. Circular reference is now on a task that does not
exist in the plan!?!?!
Any handy hints, tips or plain old fixes would be appreciated