Sounds drastic i know but......
im in the middle of rolling out the first weeks worth of timesheet to folk
here and have found out that only plan owners can approve resource timesheets
- firstly is this correct and secondly how do i sort it so that team members
have their T/s approved by team leads who are approved by PM's who are
approved by prog director ? My RBS reflect this and we are using additive
permissions - what have i missed ?
Please help or i'll be in the stuff that makes the garden grow
Cheers
Mat