Hi Mike,
I have noticed that even though I have a day rate in it is still
calculating
based on a hour (i.e. $1000/day where a day = 10 Hours) and I use the
item
for 2 hours it adds a cost of $200 to the task. I want it to show
$1000
for
the use regardless of the hours it is used. Have I missed something?
Corey,
No you haven't missed anything. I think you are just misunderstanding
how Project operates. Even though you gave a day rate, from Project's
viewpoint that is simply the cost for the equivalent of a day as
defined
under Tools/Options/Calendar tab, hours per day. So from Project's
standpoint, 2 hours in a 10 hour day is 0.2 days. If the daily rate is
$1000, then 2 hours is $200. As a matter of fact, Project actually
works
down to the tenth of a minute, so if someone only worked for 1.4
minutes
on a task and the rate was $1000/da, that would represent a cost of
$2.33.
In order to get what you want, you will have to either use a customized
field with a formula or resort to VBA. Either way, the formula should h
look at the start and finish dates to determine how many "days" to use
in the cost calculation.
John
Project MVP
:
You're welcome, Corey
Mike Glen
MS Project MVP
See
http://tinyurl.com/2xbhc for Project Tutorials
Corey wrote:
Thanks Mike.
:
Hi Corey,
Welcome to this Microsoft Project newsgroup
Yes! View the Resource Sheet and double click on the hired
equipment
resource name. In the Costs tab enter the cost and then /d for
per
day.
FAQs, companion products and other useful Project information can
be
seen at this web address:
http://project.mvps.org/faqs.htm
Hope this helps - please let us know how you get on
Have a healthy, prosperous and happy new year
Mike Glen
MS Project MVP
See
http://tinyurl.com/2xbhc for Project Tutorials
Corey wrote:
I am working on a project and have hired equipment, they are
costed
on a day basis regardless of their use, if I use it for 1 hour
or
23
hours and the cost is the same. I would also like to have a the
same setup for a equipment on a weekly hire rate.
Is there anyway that i make this happen in project ?