V
VSAT Ryan
I am looking to see if one can sum the number of hours of a task after a
certain date.
For example, my development task runs from November to February (assume non
level loading). I am looking for a way (preferably using formulas in a
number column) to sum hours (work, or baseline work would be fine) from
1/1/06 to 2/28/06, and display them in the NumberX column.
Thanks in advance!
certain date.
For example, my development task runs from November to February (assume non
level loading). I am looking for a way (preferably using formulas in a
number column) to sum hours (work, or baseline work would be fine) from
1/1/06 to 2/28/06, and display them in the NumberX column.
Thanks in advance!