G
George Thompson
I have set up a standard project calendar with weekends as
non-working days. I have a task that will be performed
through the weekend. I have not assigned any resources to
this task yet.
How do I set this up so the schedule will reflect this
task's weekend work?
What are the different calendars' priorities? I know the
resource calendar supercedes all calendars once a resource
is assigned (logical - if the resource is unavailable,
work cannot be conducted on any task during those days).
Is the task calendar only useful for defining when a task
CANNOT occur?
any help is greatly appreciated,
george
non-working days. I have a task that will be performed
through the weekend. I have not assigned any resources to
this task yet.
How do I set this up so the schedule will reflect this
task's weekend work?
What are the different calendars' priorities? I know the
resource calendar supercedes all calendars once a resource
is assigned (logical - if the resource is unavailable,
work cannot be conducted on any task during those days).
Is the task calendar only useful for defining when a task
CANNOT occur?
any help is greatly appreciated,
george