T
tjkelly
I created the enterprise resources pool for our program in Project
Server. All resources are within the same RBS. Nothing fancy. There
are 35 resources.
I can see all 35 resources.
Everyone else is only seeing only 6 of the 35 resources.
I checked the configuration of all of the records and I do not see a
difference.
Anyone have a suggestion as to where to start? Thanks
Tim
Server. All resources are within the same RBS. Nothing fancy. There
are 35 resources.
I can see all 35 resources.
Everyone else is only seeing only 6 of the 35 resources.
I checked the configuration of all of the records and I do not see a
difference.
Anyone have a suggestion as to where to start? Thanks
Tim