D
Debbie in San Diego
Does anyone use the link functionality between projects? If so, do you
experience problems in keeping the information consistent? If so, have you
figured out how to resolve it?
The situation that we have is that we have a high level project and several
lower level projects. We've taken various key tasks in the lower level
project and linked the start and finish dates in the high level project.
(doing a copy on the start date from the source project , paste special,
paste link on the start date field in the high level project and then
repeating on the finish date. We cannot link/copy the entire task into the
high level project as we're using only the start date of a series of tasks
and the end date of the ending tasks). What happens is frequently and
apparently randomly when opening the high level project, sometimes the linked
dates will have the correct dates and sometimes they are grossly wrong (going
out 5 or more years longer than is correct). HELP!!!
experience problems in keeping the information consistent? If so, have you
figured out how to resolve it?
The situation that we have is that we have a high level project and several
lower level projects. We've taken various key tasks in the lower level
project and linked the start and finish dates in the high level project.
(doing a copy on the start date from the source project , paste special,
paste link on the start date field in the high level project and then
repeating on the finish date. We cannot link/copy the entire task into the
high level project as we're using only the start date of a series of tasks
and the end date of the ending tasks). What happens is frequently and
apparently randomly when opening the high level project, sometimes the linked
dates will have the correct dates and sometimes they are grossly wrong (going
out 5 or more years longer than is correct). HELP!!!