K
Kimi Himi
Good Day. We have five departments. Each department has their projects in
separate files. Each of their projects roll up into a dept-master. The
owner of the company then has a MASTER project that each of the
depart-masters roll up into.
When you first open the MASTER project, the total cost is listed (we roll up
all cost fields). However, when you open the first departments dept-master
the total cost changes. You then must open every single sub-task in the
MASTER for the total to recalculate. It's nuts. I must have something set
wrong. I have the same problem with the dept-master.
How can I always get Project to calculate the entire set of sub projects? I
have check the options menu but that doesn't help.
Thanks in advance. Kimberly
separate files. Each of their projects roll up into a dept-master. The
owner of the company then has a MASTER project that each of the
depart-masters roll up into.
When you first open the MASTER project, the total cost is listed (we roll up
all cost fields). However, when you open the first departments dept-master
the total cost changes. You then must open every single sub-task in the
MASTER for the total to recalculate. It's nuts. I must have something set
wrong. I have the same problem with the dept-master.
How can I always get Project to calculate the entire set of sub projects? I
have check the options menu but that doesn't help.
Thanks in advance. Kimberly