Using PDS to update Resource Base Calendar

P

Paul kent

Hi , how would i update the Resource Base Calendar using
the PDS? We have multiple Calendars based on location.
Would i have to create a PDS Extender? or is there a xml i
can use to update this? Any help would be appreciated
 
M

Matthew McDermott

Paul,

According to the PDS Reference...
"The resources API does not support the creation of resource rates, resource
calendars, resource availability, contoured baseline rates, or contoured
baseline costs."

But you probably already knew that...

Matthew
 
Top