T
TroyS
I have users who want to base Earned Value on Physical % Complete.
The EntGlobal has been changed under Tools Options
However, the top summary task of the project or summary tasks in general do
NOT update based on the Physical % Completes added/updated at the task level
For example, if i have 2 tasks, one at 40% (Physical % Complete) and the
second at 25% (Physical % Complete). The summary task that includes these 2
tasks does not update NOR does the Project Summary Task (Task 0).
Any ideas on this?
Why wouldn't the summary tasks get updated?
The EntGlobal has been changed under Tools Options
However, the top summary task of the project or summary tasks in general do
NOT update based on the Physical % Completes added/updated at the task level
For example, if i have 2 tasks, one at 40% (Physical % Complete) and the
second at 25% (Physical % Complete). The summary task that includes these 2
tasks does not update NOR does the Project Summary Task (Task 0).
Any ideas on this?
Why wouldn't the summary tasks get updated?