D
DM
Hi all,
is there a way to use the information from Project Server to inform an
accounting package of the amount that needs to be billed in a particular
month? I want to be able to use percentage completion of a project to inform
the accounts package. e.g. I have a project worth $18,000 over 3 months or
so. At the end of the first month, I'm 50% complete, so I want the status of
the project at 50% complete to indicate to accounts that 50% of billing can
take place, i.e. $9000. In the 2nd and 3rd month, the remaining is split
into 25% chunks, so I am billing $4500 per month.
What accounts packages, if any have people linked to? At the moment we're
considering Sage Line 200.
Thanks for your help!
is there a way to use the information from Project Server to inform an
accounting package of the amount that needs to be billed in a particular
month? I want to be able to use percentage completion of a project to inform
the accounts package. e.g. I have a project worth $18,000 over 3 months or
so. At the end of the first month, I'm 50% complete, so I want the status of
the project at 50% complete to indicate to accounts that 50% of billing can
take place, i.e. $9000. In the 2nd and 3rd month, the remaining is split
into 25% chunks, so I am billing $4500 per month.
What accounts packages, if any have people linked to? At the moment we're
considering Sage Line 200.
Thanks for your help!