MS Project gurus,
I have an earned value problem in Project. My VAC does not equal my
BAC-EAC. I checked the internal help file and it definitely says the
following:
VAC = Budgeted At Completion (baseline cost) - Estimated At Completion
Sounds like something's wrong.
Do you know what would cause this to happen? Any way to mitigate the
problem? Thank you kindly.