J
Jerry
Hi
I have a Resource that work 10 Hours Per day and 6 days a Week. For
every week resource work i need to give him two off days (2 Weeks = 4
offDays or Vacations). The 10 Hours per day work and 6 days a week
calender is a project calender defined in enterprize global. the
Resource also have its own calender for normal 8 hoiurs work defined in
global template. All the project tasks work is calculated per 10 hours
becuase the 10 hours project celender is selected. So 1 days means 10
hour of Work. But the problem is
When i assign the resource offdays for 14 Days of duration it
calculates the work 140 Hours and duration 10 days (14 * 10). i had
choosen the task calender to none. project professional automatically
calculates the days by using the 100 / 8 hours per day which means 17.5
days. this thing is wrong. Please see the example below
Normal Activity
----------------------------------------------
Task Name : Site Work3-1
duration 14 wks
Work 840 hrs
C.Weeks 3.96
Calender Name E_Site_10x6 (Project Calendar)
ignor resource. Calender Yes
Start Date Tue 3/1/05
End Date Mon 6/6/05
Resource Name Jerry
Leave/Vacation Activity
----------------------------------------------
Task Name : Off Days
duration 14 days
Work 140 hrs
C.Weeks 3.31
Calender Name None
ignor resource. Calender No
Start Date Tue 6/7/05
End Date Thu 6/30/05
Resource Name Jerry
I want to give him vacation for 14 days. even if i had selected the
task calender to none it is calculating the dates as per project
celender. which results in wrong dates shown in task. i had tried it
using the fix duration but the task includes the normal offdays (Sat,
Sun) in the task duration as well. Why this happens is there is any
other way out to fix the vacation issue.
I need to fix this problem. Please help me in this regard
Thanks in advance
Jerry
I have a Resource that work 10 Hours Per day and 6 days a Week. For
every week resource work i need to give him two off days (2 Weeks = 4
offDays or Vacations). The 10 Hours per day work and 6 days a week
calender is a project calender defined in enterprize global. the
Resource also have its own calender for normal 8 hoiurs work defined in
global template. All the project tasks work is calculated per 10 hours
becuase the 10 hours project celender is selected. So 1 days means 10
hour of Work. But the problem is
When i assign the resource offdays for 14 Days of duration it
calculates the work 140 Hours and duration 10 days (14 * 10). i had
choosen the task calender to none. project professional automatically
calculates the days by using the 100 / 8 hours per day which means 17.5
days. this thing is wrong. Please see the example below
Normal Activity
----------------------------------------------
Task Name : Site Work3-1
duration 14 wks
Work 840 hrs
C.Weeks 3.96
Calender Name E_Site_10x6 (Project Calendar)
ignor resource. Calender Yes
Start Date Tue 3/1/05
End Date Mon 6/6/05
Resource Name Jerry
Leave/Vacation Activity
----------------------------------------------
Task Name : Off Days
duration 14 days
Work 140 hrs
C.Weeks 3.31
Calender Name None
ignor resource. Calender No
Start Date Tue 6/7/05
End Date Thu 6/30/05
Resource Name Jerry
I want to give him vacation for 14 days. even if i had selected the
task calender to none it is calculating the dates as per project
celender. which results in wrong dates shown in task. i had tried it
using the fix duration but the task includes the normal offdays (Sat,
Sun) in the task duration as well. Why this happens is there is any
other way out to fix the vacation issue.
I need to fix this problem. Please help me in this regard
Thanks in advance
Jerry