valuable template

W

Waqar Azeem

i am looking for a Template or any work around to create a report of my
project with Resource on the top bar.

For Example:

Task Duration ManHours PM[50%] Dev1 Dev2 Dev3 QA1 QA2 QA3 Start End

-----------------------------------------------------------------
TestProject - Totals 75
days 1,740 300 480 400 320 80 80 80 4/14/2009 7/31/2009
-----------------------------------------------------------------
TestProject.com 70 days 560 480 80 4/27/2009 7/31/2009
Analysis & Identifying Major Screen Layouts 5
days 40 4/27/2009 5/1/2009
TestProject.com - development 45 days 360 5/4/2009 7/3/2009
WSP Server - development 10 days 80 7/6/2009 7/17/2009
QA - Unit / Integration Testing 10 days 80 7/20/2009 7/31/2009

WM5 - TestProject Client Application 60
days 480 400 80 4/20/2009 7/10/2009
WM5 Client App - development 50 days 400 4/20/2009 6/26/2009
QA - WM5 Unit / Integration Testing 10 days 80 6/29/2009 7/10/2009

BlackBerry - TestProject Client Application 50
days 400 320 80 4/20/2009 6/26/2009
WM5 Client App - development 40 days 320 4/20/2009 6/12/2009
QA - BlackBerry Unit / Integration Testing 10
days 80 6/15/2009 6/26/2009
 
J

Jim Aksel

Try exporting the information to Excel and use a Pivot Table to make any
report you wish.
--
If this post was helpful, please consider rating it.

Jim Aksel, MVP

Check out my blog for more information:
http://www.msprojectblog.com
 