J
J.Allman
I am trying to track variances.
Ex: I have a 30 day task that has started ontime. The resource has worked
the task ontime for 15 days of work so the task is on scheduled and 50%
completed. Then the resource gets sick for 5 working days. When I update the
status date and current date and plug in the actuals for this task at the end
of the week that the resource was sick ( I added 0 work hours for this week
against the task due to the sickness) I see the SV% change indicating that we
are behind but I do not see a finish varince at all. This is due to the fact
that the [finish] has not adjusted to a later date even though we are a week
behind.
What am I doing wrong?
Ex: I have a 30 day task that has started ontime. The resource has worked
the task ontime for 15 days of work so the task is on scheduled and 50%
completed. Then the resource gets sick for 5 working days. When I update the
status date and current date and plug in the actuals for this task at the end
of the week that the resource was sick ( I added 0 work hours for this week
against the task due to the sickness) I see the SV% change indicating that we
are behind but I do not see a finish varince at all. This is due to the fact
that the [finish] has not adjusted to a later date even though we are a week
behind.
What am I doing wrong?